Batoka Hydropower (DFS)
Sector : Energy
Description : Hydroelectric plant with a capacity of 1,600 MW to enable export of electricity
Countries : Zambia/Zimbabwe, Zambezi basin
RECs : COMESA/EAC
Results (2013-2015) :
• Potential Contract type: Build, Operate, Transfer or PPP structure where both government and private are involved from the start - SPV.
• Planned commencement year for construction: 2015.
• Expected construction duration: 6 years.
• Debt – Equity ratio: 70 – 30.
• MoU was signed between Zambia and Zimbabwe in 2012, and the project should be fully implemented in a 5-6 year period. Tender is out for new feasibility studies including, social and environmental impact Assessment. Market Study completed; EIA completed and detailed feasibility techno economical completed.